Campaign objectives and timeline

Project Timeline

We’ve crafted our timeline as carefully as our project list to ensure minimal disruption to the educational experiences of current students and to ensure efficiency and cost-effectiveness. A wide array of campus improvements began in the summer of 2017 and are slated for completion in late 2019.

Phase One: Summer, 2017

1. Kindergarten renovations: COMPLETED
2. Idea & Design Lab: COMPLETED
3. Robotics Lab: COMPLETED
4. 7th/8th Grade Commons: COMPLETED

Phase Two: March-August, 2018

5. Higgins Library renovations
6. The Peck Commons construction begins

Phase Three: Summer, 2019

7. The Peck Commons construction ends
8. Kirby Lower School addition
9. Eckert-Huff Music Rooms converted to 6th-8th Grade Science Labs, completing the STEAM Wing
10. Kirby Lower School Science Lab expansion
11. Campus site work completed
12. Lindenwold Quad
13. 25 additional parking spaces
14. Kindergarten Sports Court installed
15. New playground equipment
16. Construction of Outdoor Idea & Design Lab Classroom

Questions?  Click here to find out how you can be part of The Peck Promise campaign, or contact Lauren Spirig, Campaign Director, at 973-539-8660 x135 or lspirig@peckschool.org.


timeless traditions
timely transformation

List of 3 items.

  • 247 South Street

  • Morristown, New Jersey 07960

  • 973.539.8660

Northern New Jersey's timeless and transformative independent education for grades K-8